Field Notes
Case Study: Propane Line Bore at a Hospital Campus in Anadarko, Oklahoma
By Trinity Boring Solutions · Yukon, Oklahoma · 5.0★ from 49 reviews
Not every meaningful bore is a monster crossing. This one – roughly 75 feet of poly with tracer wire at a hospital campus in Anadarko – shows what a small, well-run gas bore looks like when the site is a working medical facility and the material is owner-supplied.
The job: approximately 75 feet of 1¼-inch polyethylene propane line with tracer wire, installed by directional bore at a hospital campus in Anadarko, Oklahoma. The mechanical contractor supplied the pipe and tracer wire; we supplied the rig, crew, and drilling fluid – a clean owner-supplied-material scope.
The Challenge: Gas Work on an Active Medical Campus
Hospitals do not pause for construction. Trenching 75 feet across a medical campus means barricades, cut surfaces, and restoration around a facility that cannot compromise access. The propane scope also carries gas-work expectations: locates verified, tracer wire installed for future locatability, and a clean handoff to the mechanical contractor. Our gas line boring work runs on those rules every day.
The Approach: Small Bore, Full Discipline
The customer – the site’s mechanical contractor – provided the poly pipe and tracer wire, and our quote said exactly that, so there were no material markups hiding in the price. After locates, the crew set up clear of facility traffic, bored the ~75-foot path, and pulled the poly and tracer wire back in a single short mobilization. Owner-supplied material scopes like this are common with plumbers and mechanical contractors, and they are priced as such – see our cost guide for how that works.
The Result
The propane service went in on grade with tracer wire ready for future locates, the campus surface stayed intact, and the mechanical contractor connected their system on schedule. Small bores done right keep facilities like this off the excavation-damage statistics – the whole point of the standards covered in our standards and regulations guide.
Frequently Asked Questions
Questions customers ask about jobs like this one.
Can propane and gas lines be installed with directional boring?
Yes – polyethylene gas and propane lines are among the most common HDD products. Tracer wire is installed alongside the poly so the non-metallic line can be located electronically in the future.
What does owner-supplied material mean on a boring quote?
The customer provides the pipe, conduit, or tracer wire, and the boring contractor provides the rig, crew, tooling, and drilling fluid. The quote states that assumption up front, which keeps material markups out of the price.
Is a 75-foot bore worth hiring a directional boring contractor for?
Often, yes. On finished or sensitive sites – hospitals, campuses, commercial frontage – a short bore avoids surface cuts, barricading, and restoration that would cost more than the bore itself.
Need a gas or propane line installed without cutting your site open?
Trinity Boring Solutions is open 24 hours for directional boring across Oklahoma. 9102 NW Expressway, Yukon, OK 73099.
Anadarko Hospital Propane Bore — Field Photos



