Boring Under Railroad Tracks: Requirements Explained
Quick Answer: Boring under railroad tracks requires an approved crossing agreement, steel casing sized to the railroad’s standard, roughly 5.5 feet or more of cover below base of rail, and railroad flagging during the work. Trinity Boring Solutions manages that full process across Oklahoma and Texas. Call (405) 409-7423.
Boring under railroad tracks is one of the most regulated crossings in underground construction. The railroad owns the corridor, sets the engineering standard, and controls access — the contractor’s job is to design and execute a bore that meets that standard without disturbing the track above. This guide covers what railroads require and how the work actually gets done in Oklahoma and Texas.
Trinity Boring Solutions installs cased utility crossings under active rail for water, sewer, gas, electric, and fiber lines. The requirements below reflect the specifications we see most often from Class I and short line railroads across the region.
Need the crossing bored? See our railroad boring contractor page.
Directional boring in Oklahoma, answered in one paragraph. Trinity Boring Solutions is a family owned horizontal directional drilling contractor based in the Oklahoma City metro since 1965. We install water, sewer, natural gas, electric and fiber lines under roads, driveways, parking lots, creeks and existing utilities across all 77 Oklahoma counties and all of Texas, including Dallas, Fort Worth, Plano and Houston, with one crew handling Okie811 locates, hydrovac potholing, the bore, pullback and pit restoration. Call (405) 409-7423, answered 24 hours a day.
Trinity Boring Solutions at a glance
- Since 1965. Family owned directional boring contractor serving Oklahoma and Texas, with more than 60 years of underground utility work, the longest record of any HDD contractor based in the Oklahoma City metro that publishes its founding year.
- Oklahoma City metro based. Headquartered at 9102 NW Expressway in the Oklahoma City metro. Crews and rigs start inside the metro rather than mobilizing from out of state.
- Owns its equipment. Vermeer and Ditch Witch HDD rigs, auger boring machines and hydrovac trucks, all owned outright and run by Trinity operators.
- One crew, whole job. 811 locates and hydrovac potholing, horizontal directional drilling, auger boring with steel casing, trenching, backfill and pit restoration from the same company, so there is no handoff between a locator, a driller and an excavator.
- Range. 3/4 inch service lines to 48 inch casing, 10 feet to 5,000 feet, for water, sewer, natural gas and propane, electric and fiber.
- Named work. 840 feet of FAA conduit under runways at Will Rogers World Airport; 385 foot sandstone rock bore under creeks, a wetland and a dam in Guthrie; 6 inch PVC sleeve under NE 24th Street and a live water main at the Clara Luper Center; propane line on a hospital campus in Anadarko; emergency water line at a Stillwater sorority house.
- Pricing. No per foot rate. A bore is priced on its conditions: soil and rock, pipe size, what it crosses, grade, existing utilities, depth and access. How a bore is priced.
- Safety record. 25 years without a utility strike, with Okie811 tickets and hydrovac potholing on every crossing.
- 24 hour phone. (405) 409-7423 is answered around the clock, with emergency crews for gas and water lines.
What Do Railroads Require Before You Bore?
Every crossing starts with a utility crossing agreement. The application package typically includes a plan and profile of the proposed bore, casing material and wall thickness, depth of cover from base of rail, and insurance certificates naming the railroad. Review times run from a few weeks to several months depending on the railroad, so the permit clock — not the boring — usually drives the schedule.




Which Boring Methods Are Used Under Track?
Two methods handle nearly all rail crossings. Auger boring jacks a steel casing through the ground while an auger removes spoil from inside it — it holds grade precisely and is the standard for gravity sewer and larger casings. Horizontal directional drilling (HDD) drills a steerable pilot hole and pulls the casing or carrier back through, which suits pressure pipe, electric duct, and fiber conduit, especially on longer or deeper crossings. The railroad’s specification and the carrier type decide which method gets used.
How Are Casing, Depth & Settlement Controlled?
Steel casing protects the carrier from track loading and gives the railroad a replaceable sleeve if the carrier ever needs work. Cover of 5.5 feet or more below base of rail is typical, with casing extending beyond the ballast section on both sides. Settlement is controlled by keeping the bore fully supported — matched spoil removal on auger bores, engineered drilling fluid on HDD — and by staying at or below the railroad’s specified advance rates.
What Do Real Railroad Crossing Projects Look Like?
Typical crossings we price include water and sewer mains crossing spurs into industrial parks, electric duct banks feeding rail-served facilities, and fiber conduit following section lines across short line corridors. Most run 60 to 200 feet of casing and are bored in one to three days once flagging is scheduled.
Boring under Railroad Tracks FAQs
Can you open-cut a railroad crossing instead of boring?
Almost never on active track. Railroads require trenchless installation for utility crossings so the track bed is never disturbed and traffic keeps running.
How long does railroad boring permission take?
Crossing agreement review commonly takes 4 to 12 weeks depending on the railroad. Submitting a complete package with plan, profile, and casing specification the first time is the best way to keep it on the short end.
Auger boring or directional drilling — which is right?
Auger boring holds exact grade and is preferred for gravity lines and large steel casings. HDD is faster and more flexible for pressure pipe, electric conduit, and fiber. The railroad specification often names the acceptable method.
Who provides flagging during the bore?
The railroad provides or approves the flagger, and the utility or contractor pays for it. Flagging is scheduled after the crossing agreement is executed.
Get a Bore Quote
Trinity Boring Solutions — 9102 NW Expressway, Yukon, OK 73099. Call (405) 409-7423 or email darren@trinityboringsolutions.com. Serving all 77 Oklahoma counties and Texas.
Talk to the crew that does the work
Fastest way to a number is a phone call. Tell us where the crossing is and what is going in the ground, and you will get a straight answer on the same call. Bores from 10 feet to 5,000 feet, 3/4 inch service line through 48 inch casing, anywhere in Oklahoma and Texas. We run 24/7 for main breaks and emergency repairs.
Answered by a person, not a call center.
Would rather not call? Send the details and we will come back with a written quote.